PROGRESS REPORT | JANUARY 2026


Redwood Lakeside, Phuket January 2026 focused on continued architectural progression

across active villas, steady advancement of new structural

works, and further completion of infrastructure and landscaping.

The project maintains a high standard of organization and

quality, shaping a cohesive and well-considered residential

environment. Show villas remain in near-complete condition,

requiring only minor final finishing works.

Key Achievements / January 2026

Ongoing Architectural Progress Across All Active Villas:

Architectural works advanced consistently across A-, B-,and C-Series villas, with multiple units moving closer to final completion.

Advancement of New Structural Zones:

Structural works progressed on Villas C04 and A09, while

initial construction continued on D-Series villas (D01,

D02).

Infrastructure and Hardscape Near Finalization:

infrastructure progressed to 93%, with hardscape works

reaching 91%, focusing on final surface finishes and

detailing.

Landscaping Works Accelerated:

Landscaping advanced notably from approximately

45–50% to 58% by the end of the month.

Show Villas Maintained at High Readiness:

Show Villas A11 and C05 remained at 99%, requiring only

minor finishing works.

Public Areas & Infrastructure / January 2026 Infrastructure and common areas continued progressing toward

Final completion:

General Infrastructure: Advanced from 90–92% to 93%

Hardscape: Progressed from 88–89% to 91%

Retention Wall: Maintained at 100%

Pier & Bridge: Maintained at 100%

Fence (Plots A & C): Maintained at 99%

Landscaping: Progressed steadily to 58%

Community Center: Maintained at 99%, pending final

handover procedures

Villas Construction / January 2026

Structural Works (ST)

Structural activities continued for newly introduced villas.

Villa C04: Progressed from 18–20% to 25%

Villa A09: Advanced from 28–30% to 40%

Villas D01 & D02: Maintained at 5%, with initial

groundwork completed

These works ensure a stable pipeline for upcoming

architectural phases.

Architectural Works (AR)

Architectural finishing remained the main activity throughout the

site:

A-Series Villas

A02: Progressed from 43% to 54%

A04: Advanced from 50% to 55%

A06: Progressed to 50%

A08: Maintained at 42%●

A10: Advanced to 50%

B-Series Villas

B03: Progressed from 80% to 82%

B06 & B09: Advanced to 89%

B01, B02, B04, B05, B07, B08: Maintained steady

progress at 70%

C-Series Villas

Villa C03: Maintained at 99%, effectively complete

pending final detailing

Villas C01 & C02: Maintained at 60–62%

Villa C05 (Show Villa): Maintained at 99%

Show Units / January 2026

Show Villa A11: Maintained at 99%

Show Villa C05: Maintained at 99%

Both show units remain in the final detailing stage, with only

minor finishing works outstanding.

 
 
 