PROGRESS REPORT | JANUARY 2026
- Mikhail Drozdovski
- 4 days ago
- 2 min read

Redwood Lakeside, Phuket January 2026 focused on continued architectural progression
across active villas, steady advancement of new structural
works, and further completion of infrastructure and landscaping.
The project maintains a high standard of organization and
quality, shaping a cohesive and well-considered residential
environment. Show villas remain in near-complete condition,
requiring only minor final finishing works.
Key Achievements / January 2026
Ongoing Architectural Progress Across All Active Villas:
Architectural works advanced consistently across A-, B-,and C-Series villas, with multiple units moving closer to final completion.
Advancement of New Structural Zones:
Structural works progressed on Villas C04 and A09, while
initial construction continued on D-Series villas (D01,
D02).
Infrastructure and Hardscape Near Finalization:
infrastructure progressed to 93%, with hardscape works
reaching 91%, focusing on final surface finishes and
detailing.
Landscaping Works Accelerated:
Landscaping advanced notably from approximately
45–50% to 58% by the end of the month.
Show Villas Maintained at High Readiness:
Show Villas A11 and C05 remained at 99%, requiring only
minor finishing works.
Public Areas & Infrastructure / January 2026
Infrastructure and common areas continued progressing toward
Final completion:
General Infrastructure: Advanced from 90–92% to 93%
Hardscape: Progressed from 88–89% to 91%
Retention Wall: Maintained at 100%
Pier & Bridge: Maintained at 100%
Fence (Plots A & C): Maintained at 99%
Landscaping: Progressed steadily to 58%
Community Center: Maintained at 99%, pending final
handover procedures
Villas Construction / January 2026
Structural Works (ST)
Structural activities continued for newly introduced villas.
Villa C04: Progressed from 18–20% to 25%
Villa A09: Advanced from 28–30% to 40%
Villas D01 & D02: Maintained at 5%, with initial
groundwork completed
These works ensure a stable pipeline for upcoming
architectural phases.
Architectural Works (AR)
Architectural finishing remained the main activity throughout the
site:
A-Series Villas
A02: Progressed from 43% to 54%
A04: Advanced from 50% to 55%
A06: Progressed to 50%
A08: Maintained at 42%●
A10: Advanced to 50%
B-Series Villas
B03: Progressed from 80% to 82%
B06 & B09: Advanced to 89%
B01, B02, B04, B05, B07, B08: Maintained steady
progress at 70%
C-Series Villas
Villa C03: Maintained at 99%, effectively complete
pending final detailing
Villas C01 & C02: Maintained at 60–62%
Villa C05 (Show Villa): Maintained at 99%
Show Units / January 2026
Show Villa A11: Maintained at 99%
Show Villa C05: Maintained at 99%
Both show units remain in the final detailing stage, with only
minor finishing works outstanding.